New York City blackout of 1977 facts for kids
The New York City blackout of 1977 was an electricity blackout that affected most of New York City on July 13–14, 1977. The only unaffected neighborhoods in the city were in southern Queens (including neighborhoods of the Rockaways), which were part of the Long Island Lighting Company system, as well as the Pratt Institute campus in Brooklyn, and a few other large apartment and commercial complexes that operated their own historic power generators.
Unlike other blackouts that affected the region, namely the Northeast blackouts of 1965 and 2003, the 1977 blackout was confined to New York City and its immediate surrounding areas. The 1977 blackout also resulted in citywide looting and other criminal activity, including arson, unlike the 1965 and 2003 blackouts.
Contents
Prelude
Lightning damage
The events leading up to the blackout began on July 13 at 8:34 p.m. EDT on Wednesday, with a lightning strike at Buchanan South, a substation on the Hudson River, tripping two circuit breakers in Buchanan, New York. The Buchanan South substation converted the 345,000 volts of electricity originating from the 900 MW Indian Point nuclear generating station to lower voltage for commercial use. A loose locking nut combined with a slow-acting upgrade cycle prevented the breaker from reclosing and allowing power to flow again.
A second lightning strike caused the loss of two 345 kV transmission lines, subsequent reclose of only one of the lines, and the loss of power from the nuclear plant at Indian Point. As a result of the strikes, two other major transmission lines became overloaded. Per procedure, Consolidated Edison, the power provider for New York City and some of Westchester County, tried to bring a fast-start generating station online at 8:45 p.m. EDT; however, no one was manning the station, and the remote start failed.
At 8:55 p.m., there was another lightning strike at the Sprain Brook substation in Yonkers, which took out two additional critical transmission lines. As before, only one of the lines was automatically returned to service. This outage of lines from the substation caused the remaining lines to exceed the long-term operating limits of their capacity. After this last failure, Con Edison had to manually reduce the loading on another local generator at their East River facility, due to problems at the plant. This made an already dire situation even worse.
Power reductions
At 9:14 p.m., over 30 minutes from the initial event, New York Power Pool Operators in Guilderland called for Con Edison operators to "shed load." In response, Con Ed operators initiated first a 5% system-wide voltage reduction and then an 8% reduction. These steps had to be completed sequentially and took many minutes. These steps were done in accordance with Con Edison's use of the words "shed load" while the Power Pool operators had in mind opening feeders to immediately drop about 1500 MW of load, not reduce voltage to reduce load a few hundred MW.
At 9:19 p.m., the final major interconnection to Upstate New York at Leeds substation tripped due to thermal overload which caused the 345kV conductors to sag excessively into an unidentified object. This trip caused the 138 kV links with Long Island to overload, and a major interconnection with the New Jersey Public Service Electric and Gas Company (PSEG) began to load even higher than previously reported.
At 9:22 p.m., Long Island Lighting Company opened its 345 kV interconnection to Con Edison to reduce power that was flowing through its system and overloading 138 kV submarine cables between Long Island and Connecticut. While Long Island operators were securing permission from the Power Pool operators to open their 345 kV tie to New York City, phase shifters between New York City and New Jersey were being adjusted to correct heavy flows, and this reduced the loading on the 115 kV cables. The Long Island operators did not notice the drop in 115 kV cable loadings and went ahead with opening their 345 kV tie to New York City.
At 9:24 p.m., the ConEdison operator tried and failed to manually shed load by dropping customers. Five minutes later, at 9:29 p.m., the Goethals-Linden 230 kV interconnection with New Jersey tripped, and the Con Edison system automatically began to isolate itself from the outside world through the action of protective devices that remove overloaded lines, transformers, and cables from service.
Blackout
Power failure
Con Ed could not generate enough power within the city, and the three power lines that supplemented the city's power were overtaxed. Just after 9:27 p.m., the biggest generator in New York City, the 990 MW Ravenswood Generating Unit No. 3 (also known as "Big Allis"), shut down and with it went all of New York City.
By 9:37 p.m., the entire ConEdison power system shut down, almost exactly an hour after the first lightning strike. By 10:26 p.m., operators started a restoration procedure. Power was not fully restored until late the following day. Among the outcomes of the blackout were detailed restoration procedures that are well documented and used in operator training to reduce restoration time.
Shea Stadium
Shea Stadium went dark at approximately 9:30 p.m., in the bottom of the sixth inning, with Lenny Randle at bat. The New York Mets were losing 2–1 against the Chicago Cubs. Jane Jarvis, Shea's organist and "Queen of Melody", played "Jingle Bells" and "White Christmas." The game was completed two months later on September 16, with the Cubs winning 5–2. The Yankees were on the road at Milwaukee; less than a week later, Yankee Stadium hosted the All-Star Game on Tuesday, July 19.
Return of power
It was not until the next morning that power began being restored to those areas affected. Around 7 a.m. on July 14, a section of Queens became the first area to get power back, followed shortly afterward by Lenox Hill, Manhattan; the neighboring Yorkville area on the Upper East Side of Manhattan, though, was one of the last areas to get power back that Thursday evening. By 1:45 p.m., service was restored to half of Con Edison's customers, mostly in Staten Island and Queens. It was not until 10:39 p.m. on July 14 that the entire city's power was back online.
For much of July 14, most of the television stations in New York City were off the air (as the areas where those TV stations were located were still without power for much of the day), although WCBS-TV (Channel 2) and WNBC-TV (Channel 4) did manage to stay on the air thanks to gas and diesel-fueled generators, resuming their broadcasts only 25 and 88 minutes after the blackout began, respectively. Although much of New York City was still without power, Belmont Park (a racetrack on the border of Queens and Nassau County in Elmont) did stage their scheduled racing program that afternoon in front of a relatively sparse crowd, as many thought racing would be cancelled that day due to the blackout.
Legacy
Music
There is a popular story that during the blackout numerous looters stole DJ equipment from electronics stores, and this helped spark the hip hop genre -- but the only evidence is some speculation by two early DJs, DJ Disco Wiz and Curtis Fisher, who made the suggestion in an interview for Jim Fricke and filmmaker Charlie Ahearn, who printed it in their book Yes Yes Y'all. Caz later expanded from speculation to mythology, saying in a Slate article and podcast that, when the power went out, he and Wiz were playing records, running their equipment from an outlet in a park. At first they thought the outage was local and caused by something they had done, but realized when they heard stores closing that it was citywide and took advantage of the community's vulnerability to steal a mixing board from a local business. "I went right to the place where I bought my first set of DJ equipment, and I went and got me a mixer out of there." However, most early DJs dismiss this story as inaccurate, with Afrika Bambaataa stating that “Blackout '77 got nothin' to do with hip-hop . . . Whoever came with that is talking a lot of BS.”
David Bowie has stated the blackout was a possible influence on his 1977 song Blackout, "I can't in all honesty say that it was the NY one, though it is entirely likely that that image locked itself in my head."
Complications
The blackout also caused complications for the producers of the film Superman, who were shooting in the area.
The city was eventually given over $11 million by the Carter administration to pay for the damages of the blackout.
Beame accused Con Edison of "gross negligence" but would eventually feel the effect himself. In the mayoral election that year, Beame finished third in the Democratic primary to Ed Koch and Mario Cuomo. Koch would go on to win the general election.
The operating entities in New York fully investigated the blackout, its related causes, and the operator actions. They implemented significant changes, which are still in effect today, to guard against a similar occurrence. Despite these safeguards, there was a blackout in August 2003, although this was caused by a power system failure as far away as Eastlake, Ohio.
On July 13, 2019, on the 42nd anniversary of the event, a Con Edison blackout occurred, affecting 73,000 people on Manhattan's West Side.
See also
In Spanish: Apagón de Nueva York de 1977 para niños