Kosciuszko Bridge facts for kids

Kids Encyclopedia Facts
Kosciuszko Bridge 2017-02a jeh
New and old Kosciuszko bridges in February 2017. New cable-stayed bridge is in foreground left. The 1939 truss bridge is behind it and right.
Kosciuszko Bridge is located in New York City
Kosciuszko Bridge
Location in New York City

The Kosciuszko Bridge is a cable-stayed bridge over Newtown Creek in New York City, connecting Greenpoint in Brooklyn to Maspeth in Queens. The bridge consists of a pair of cable-stayed bridge spans: the eastbound span opened in April 2017, while the westbound span opened in August 2019. An older bridge, a truss bridge of the same name that was located on the site of the westbound cable-stayed span, was originally opened in 1939 and was closed and demolished in 2017. The crossing is part of the Brooklyn–Queens Expressway (BQE), which carries Interstate 278.

The older truss bridge replaced a swing bridge called the Meeker Avenue Bridge, which connected Meeker Avenue in Brooklyn to Laurel Hill Boulevard in Queens. The old Kosciuszko Bridge, originally also called the Meeker Avenue Bridge, carried six lanes of traffic, three in each direction. In 1940, a year after opening, the bridge was renamed after Polish military leader Tadeusz Kościuszko, who fought alongside the Americans in the American Revolutionary War.

In 2014, a contract was awarded and work begun to build one of two replacement bridges with more capacity, with the first bridge initially carrying bidirectional traffic. The replacement bridges have the same name as the original bridge, and are both cable-stayed bridges that will each carry one direction of traffic. The first bridge, located south of the old truss bridge, opened on April 27, 2017, with three lanes in each direction. Once the old bridge was demolished via controlled explosion in October 2017, a new westbound cable-stayed bridge with four lanes and a bike/pedestrian path started construction on the site of the old bridge. The first cable-stayed bridge became eastbound-only with five lanes when the westbound bridge opened on August 29, 2019.


Original bridges

Quick facts for kids
Kosciuszko Bridge
Kosciusko bridge from up Newtown Creek jeh.jpg
1939 bridge as seen from upstream Queens side, 2008
Coordinates 40°43′40″N 73°55′45″W / 40.7277°N 73.9291°W / 40.7277; -73.9291
Crosses Newtown Creek
Locale Brooklyn and Queens, New York City
Maintained by New York State Department of Transportation
Preceded by Greenpoint Avenue Bridge
Followed by Grand Street Bridge
Characteristics
Design Truss bridge
Total length 6,021 feet (1,835 m)
Longest span 300 feet (91 m)
Clearance below 125 feet (38 m)
History
Opened August 23, 1939; 85 years ago (1939-08-23)
Closed April 27, 2017; 7 years ago (2017-04-27)
Statistics
Daily traffic 162,581 (2016)

The first bridge on the site was built in 1803 through an Act of Legislature authorizing the building of a Toll Bridge over Newtown Creek: this bridge charged one cent per foot passenger, which was why the bridge was called the "Penny Bridge." The original bridge was replaced several times. Also called Meeker Avenue Bridge, the structure in use since 1894 was still informally known by some as the Penny Bridge. The bridge structures connected Meeker Avenue in Brooklyn to Review Avenue and Laurel Hill Boulevard in Queens.

Until 1888, the bridge was operated by private companies and thereafter became the property of the people. In 1896, the bridge became the property of the city of Brooklyn and in 1898, upon consolidation, it was taken over by the Department of Bridges of the Greater City of New York.

The Kosciuszko Bridge, originally referred to as the Meeker Avenue Bridge, opened on August 23, 1939. It was built at a cost of $6 million to $13 million (equal to between $126,000,000 and $273,000,000 in 2022 dollars). The Meeker Avenue Bridge's design and form were vastly different than the first Meeker Avenue Bridge. The earlier was a swing drawbridge and carried a two-lane, 20-foot-wide (6.1 m) roadway and two sidewalks. The new bridge carried two three-lane concrete roadways each 32 feet (9.8 m) wide and separated by a 4-foot (1.2 m) median, as well as walkways alongside it. Additionally, this new bridge structure contained 16,315 short tons (14,801 t) of steel, along with 88,120 cubic yards (67,370 m3) of concrete masonry.

One person who helped build the new $1.5 million Meeker Avenue Bridge was John Kelly, a former Navy deep-sea diver from Greenpoint, Brooklyn, who became famous for helping to work on the new bridge. In 1938, he completed his task of building a cofferdam, a box-like structure made of 250 steel sheets. This enabled workmen to operate and build an underwater pier in dry surroundings on the Brooklyn side of the new bridge; after that, Kelly began cutting away cofferdam bracings on the Queens side, at Laurel Hill Boulevard and Review Avenue. One of the tools he worked with was an underwater-operated cutting torch, which burned oxygen, hydrogen, and compressed air.

The city government officially renamed the bridge after Tadeusz Kościuszko, a Polish volunteer who was a General in the American Revolutionary War, on July 10, 1940. On September 22, 1940, months after the conquest of Poland, Mayor Fiorello La Guardia led a ceremony in which he formally renamed the new Meeker Avenue Bridge over Newtown Creek after Kościuszko. The naming occurred in the presence of 15,000 people, mainly Polish-American residents and city and state government representatives, some stating that the spirit of Polish liberty would never die. There were parades at both ends of the bridge, and La Guardia also unveiled plaques that commemorated the new name. In making an ovation, the mayor described President Franklin D. Roosevelt, like Kościuszko, as a "champion of liberty during a difficult period", referring to World War II in which Poland was occupied by Germany. He also stated, "I am confident that Poland will live again. Any land that breeds such lovers of freedom can never be kept enslaved. The Polish people may be captive, but the flaming spirit of Polish liberty will never be destroyed." Two of the bridge towers were surmounted with eagles, one with the Polish eagle and the other the American eagle.

A repaving project in 1958 temporarily made the bridge a one-way operation for five months. Only Queens-bound traffic was allowed during afternoons and evenings, while only Brooklyn-bound traffic was permitted at all other times. In 1965, the Kosciuszko Bridge was widened, and the approach ramps on the Brooklyn–Queens Expressway and Long Island Expressway were rebuilt into an incomplete partial cloverleaf interchange for $32.7 million. The BQE was rebuilt from Cherry Street, at the Brooklyn end of the bridge, to Queens Boulevard in Queens. A small section of the LIE was reconstructed near its interchange with the BQE, between Van Dam Street and Maurice Avenue. This necessitated temporary detour routes around the bridge. At this time the original bridge's walkways were removed to add more car lanes.

Replacement

Kosciuszko Bridge
New Kosciuszko Bridge rendering.jpg
Rendering of replacement when both bridges are completed.
Coordinates 40°43′40″N 73°55′45″W / 40.7277°N 73.9291°W / 40.7277; -73.9291
Carries I-278 (Brooklyn-Queens Expressway)
Crosses Newtown Creek
Locale Brooklyn and Queens, New York City
Maintained by New York State Department of Transportation
Preceded by Greenpoint Avenue Bridge
Followed by Grand Street Bridge
Characteristics
Design Cable-stayed bridge
Longest span 1,001 feet (305 m)
Clearance below 90 feet (27 m)
History
Opened April 27, 2017; 7 years ago (2017-04-27) (eastbound)
August 29, 2019; 5 years ago (2019-08-29) (westbound)

The 1939 bridge, which was only meant to serve 10,000 vehicles per day, carried 18 times that amount of traffic when it became part of the Interstate Highway System. It was not up to Interstate standards since it did not have any drainage pipes or shoulders. By the 1990s, the bridge was deteriorating and heavily congested. After an 18-month study in 1994–5, State Transportation Department officials concluded that in order to relieve congestion on the busy span, a new $100 million bridge, which included an additional three lanes, should be built next to the original six-lane Kosciuszko Bridge. This new bridge would be part of a renovation project planned for the entire crossing. DOT Supervisor Peter King stated that this new bridge may be required to avoid severe traffic backups on neighborhood streets surrounding the bridge during renovation of the Kosciuszko. King felt that in order to resolve the increasing number of severely congested streets and intersections, "a second parallel span" may be the answer.

Two pylons built, June 2016
Traveling across the new eastbound bridge, April 2017
Seen at night, October 2018

Construction of eastbound bridge

In 2009, it was decided to replace the 1939 structure with a new bridge, which was to consist of a five-lane eastbound span, a four-lane westbound span, a bike path, and a walkway. Four designs were considered for the new structure: a cable-stayed bridge, a through arch bridge, a box girder bridge, and a deck arch bridge. The cable-stayed bridge design, selected after a public review process, makes the replacement bridge the first vehicular cable-stayed bridge in New York City since the Brooklyn Bridge (which has a hybrid suspension/cable-stayed design), as well as the first major new bridge in New York City since the Verrazano-Narrows Bridge's completion in 1964.

Construction was originally expected to begin in 2013, but was then delayed to winter 2014. About 140 trees were removed on both sides of the bridge in April 2014 in preparation for the rebuilding, though officials say twice the number of trees will be replanted once the bridge's reconstruction was completed.

On May 23, 2014, a $554.77 million design-build contract, for the construction of the eastbound span and demolition of the old bridge was awarded to a team consisting of Skanska, which will be managing partner; Ecco III of Yonkers; Kiewit Corporation of Nebraska; and HNTB of Kansas as the lead design firm. It is the largest single contract ever awarded by the New York State Department of Transportation. The work involved building a new eastbound viaduct, which was completed in 2017; the existing eastbound structure would then be demolished. The westbound viaduct would then be completed by 2020. The new bridges are being built since the Kosciuszko Bridge is known as a notorious traffic bottleneck; according to The New York Times, it is "perhaps the city's most notorious [bridge], hated and feared by drivers and synonymous in traffic reports with bottlenecks, stop-and-go and general delay." The bridges would reduce delays by up to 65% during rush hours, as well as provide a new pedestrian/bicycle connection between the boroughs.

On December 4, 2014, work began on the eastbound bridge, which entailed temporarily narrowing the Meeker Avenue entrance on the Brooklyn side on the bridge in order to widen it in the long run. Work was to take place in the daytime, temporarily causing more traffic congestion. By August 2015, the two pylons for the eastbound bridge, as well as part of the bridge structure, were under construction. The 287-foot-high (87 m) pylons were sunk 150 to 185 feet (46 to 56 m), with each pylon resting on four foundations at that depth. After the pylons were completed, a supporting steel-and-concrete deck section called a pier table was built between the two pylons. The other deck sections were then built outward from the pier table, with two cables supporting each section, creating a 1,001-foot-long (305 m) deck supported by 56 cables in total. A 4,000-short-ton (3,600-long-ton) counterweight was built under the western section of the eastbound bridge since the eastern section was longer and heavier. The new bridge was built to withstand a century's worth of traffic.

The new eastbound bridge, which initially hosted both directions of traffic, opened ahead of schedule on April 27, 2017, with a ceremony attended by Governor Andrew Cuomo. The bridge is the first of several bridges citywide to feature an advanced lighting system – part of Governor Cuomo's "New York Harbor of Lights" initiative – which would allow the bridge to display light shows as a tourist attraction. At that time, five of six lanes of traffic were shifted to the new bridge, with a single lane of westbound traffic temporarily using the old bridge until the end of the month. The new bridge kept the same name as the original.

Demolition and construction of westbound bridge

K-bridge north approach broken jeh
Collapsed approach at Queens (east) end

Part of the original structure was set to be demolished by controlled explosion in summer 2017 so that work on the new westbound bridge could begin soon after. This type of demolition, beginning with Governor Cuomo personally pushing the button to detonate the bridge, saved seven to nine months compared to if the entire bridge had been carefully dismantled. The new westbound span and pedestrian/bike lanes would be ready in 2020, providing the bridge with extra traffic capacity. Initial reports speculated that the explosion date would be July 11. Instead, the main span of the bridge was lowered onto a barge, and the approaches would then be exploded. This updated plan was meant to be environmentally friendly since less of the bridge would be scattered into the creek below. At the time there was no date set for the actual demolition.

The old bridge's main span was lowered onto two barges tied together, and on July 26, 2017, the main span was shipped to New Jersey to be recycled. This marked the completion of the first phase of the old bridge's demolition. The approaches to the former main span were demolished on October 1, 2017, with the detonation of 944 small explosive charges. This was the largest explosive demolition in New York City and the first of a bridge there. The state would recycle the twenty trusses from the approaches, which weigh a combined 22,000,000 pounds (10,000,000 kg).

Koscuiuszko walkway & cables jeh
Westbound span, opened September 2019; the walkway and bikeway is to the left

Afterward, construction started on the westbound bridge. Work progressed quickly, and in May 2019, Cuomo announced that the westbound bridge would open by that September. The opening date of the westbound bridge was later revised to August 29, 2019. The westbound bridge opened as scheduled on that date, though pedestrians and bicyclists were allowed to cross the day before. As part of the construction of the westbound span, it was announced that a 7-acre (2.8 ha) park would be built in the unused space beneath the Brooklyn approach, and would open in 2020. The park, to be named "Under the K", would contain four segments: a pathway called the Arm, a multi-use zone called K-flex 1, a performance space called K-flex 2, and a waterfront seating area called Creekside.