kids encyclopedia robot

Watauga Dam facts for kids

Kids Encyclopedia Facts
Quick facts for kids
Watauga Dam
Watauga dam1.JPG
Watauga Dam (from upstream), June, 2008
Official name Watauga Dam
Location Carter County, Tennessee, United States
Coordinates 36°19′24″N 82°7′19″W / 36.32333°N 82.12194°W / 36.32333; -82.12194
Construction began February 16, 1942
Opening date December 1, 1948
Operator(s) Tennessee Valley Authority
Dam and spillways
Impounds Watauga River
Height 318 feet (97 m)
Length 900 feet (270 m)
Reservoir
Creates Watauga Lake
Total capacity 677,000 acre⋅ft (835,000 dam3)

Watauga Dam is a hydroelectric and flood control dam on the Watauga River in Carter County, in the U.S. state of Tennessee. It is owned and operated by the Tennessee Valley Authority, which built the dam in the 1940s as part of efforts to control flooding in the Tennessee River watershed. At 318 feet (97 m), Watauga is the second-highest dam in the TVA river and reservoir system (behind only Fontana), and at the time of its completion was one of the highest earth-and-rock dams in the United States. The dam impounds the TVA Watauga Reservoir of 6,430 acres (2,600 ha), and its tailwaters feed into Wilbur Lake. The Appalachian Trail crosses the top of Watauga Dam.

Watauga Dam is named after the Watauga River. The river was named after a Cherokee settlement— the Watauga Old Fields— once located along the river at modern Elizabethton. It was listed on the National Register of Historic Places on August 11, 2017.

Location

Watauga Dam is located 37 miles (60 km) above the mouth of the Watauga, at a point where the westward-flowing river veers north to slice a water gap through the middle of Iron Mountain. The dam is about 5 miles (8.0 km) downstream from Butler, Tennessee and 10 miles (16 km) upstream from Elizabethton. Watauga Lake stretches for 16.7 miles (26.9 km) along the river, nearly reaching the Tennessee-North Carolina state line, and includes parts of Carter County and Johnson County in Tennessee. Roan Creek, Cobb Creek, and the Elk River form substantial embayments along the reservoir.

Capacity

Watauga Dam is an earth-and-rock dam 318 feet (97 m) high and 900 feet (270 m) long, and has a generating capacity of 57,600 kilowatts. The dam's fixed-crest morning glory spillway has a maximum discharge of 73,200 cubic feet per second (2,070 m3/s). Watauga Lake has 106 miles (171 km) of shoreline and a storage capacity of 677,000 acre⋅ft (835,000 dam3), of which 152,829 acre⋅ft (188,512 dam3) is reserved for flood control. The reservoir's operating levels vary by about 9 feet (2.7 m) in a typical year.

Watauga's powerhouse is located nearly a mile downstream from the dam, and is connected to the reservoir intake by a 3,700-foot (1,100 m) tunnel. Just above the powerhouse, the tunnel splits into two steel conduits that carry the water to a valve house just above the turbines.

Background and construction

Watauga-dam-tva1
Watauga Dam, (from upstream), circa 1950.

The hydroelectric potential of the Watauga River had been recognized since the early 1900s, when the Watauga Power Company built Wilbur Dam 3 miles (4.8 km) downstream from the modern Watauga Dam site. In the 1920s, the Holston River Power Company began making plans for a large-scale dam-building project in the South Fork Holston River watershed, and had identified two possible dam sites along the Watauga, one of which was the current site of Watauga Dam (the company called it the "Cardens Bluff" site). In the early 1940s, the Tennessee Valley Authority— which had assumed oversight of flood control operations in the Tennessee River watershed in the previous decade, suggested a dam at the Cardens Bluff site to provide badly needed flood storage and help with the region's World War II energy demands. The dam project garnered widespread local support, especially from Elizabethton, which had been ravaged by a flood in 1940. The Watauga project was authorized December 17, 1941, and work on the dam began on February 16, 1942.

Watauga-dam-tva2
Construction work at the Watauga Dam site, circa 1940s

The construction of Watauga Dam and its reservoir required the purchase of 11,700 acres (47 km2) of land, 1,663 acres (6.7 km2) of which had to be cleared. 761 families, 1,281 graves, and 55 miles (89 km) of roads had to be relocated, and three new bridges were built. Wilbur Dam, located just 3 miles (4.8 km) downstream, had to be raised and outfitted with a new spillway. The town of Butler had to be moved. In October 1942, the U.S. War Production Board ordered TVA to halt the Watauga project, deeming it unnecessary for the nation's wartime needs. TVA spent several weeks securing the dam site and tunnel, and the project was set aside until the end of the war. Construction proceeded on May 22, 1946.

Watauga Dam was completed and its gates opened December 1, 1948. The dam's first generator went online August 30, 1949, and the second went online September 29, 1949. The total cost of the Watauga project was just over $32 million.